TEK-Ocean’s client requested that their Subsea Tree Handling Cap be re-verified for use.

About Project

Project
Objective

  • Determine if the SST Handling Caps comply with the relevant lifting codes and standards.
  • Confirm that their condition is fit for use.
  • Issue a certificate of compliance verifying they are fit for use.
About Project

Project
Outcome

  • Determine which lifting codes are applicable and best suited for the equipment’s application.
  • Carry out engineering verification using FEA and first principals checks.
  • Conduct proof load testing:
    • Utilising TR16 profile on an ex-campaign subsea tool,
    • Design a test jig allowing use of hydraulic jacks to apply the proof load.
  • Provide an engineering report including engineering verification, load testing procedure and certificate of load test.